New Engineering Contract
The IRTS project adopts the "New Engineering Contract" (NEC) form of contract. Under the NEC, DSD, the project consultant and the contractor foster a relationship through partnering mutual trust and co-operation. On this basis, the parties collaborate closely to foresee and early resolve potential problems, thereby minimizing disputes and avoiding delay and effectively enhancing project cost control.
Through close collaboration from all parties involved, the project was completed one month ahead of schedule.