PWP No. 4395DS

Tolo Harbour Sewerage of Unsewered Areas, Stage 2 Phase 1

Project Scope
The scope of the project comprises the construction of about 12 kilometres of sewers in nine unsewered areas in Sha Tin, namely Siu Lek Yuen, Ngau Pei Sha, Tsok Pok Hang, Sha Tin Heights, Fui Yiu Ha, Kwai Tei New Village, Sha Tin Fishermen’s New Village (also known as Ah Kung Kok Fishermen Village), Kau To and Tin Liu, as well as two unsewered areas in Tai Po, namely, Ha Wun Yiu and Shan Tong, and one sewage pumping station at Kau To in Sha Tin.
Major Improvements and Benefits
To improve the water quality in Tolo Harbour and the sanitary condition of 11 unsewered villages/areas in Sha Tin and Tai Po.
Consultants
AECOM Asia Company Limited
Contractor
Top Express Construction Engineering Limited
Hsin Chong Aster Building Services Limited
Contract No.
DC/2013/01, DE/2015/07
Project Commencement Date
31 July 2013
Project Completion Date
30 April 2018
Project estimate
About $364.7 million
Controlling Division
Consultants Management Division
Type
Sewerage and sewage treatment
District
Sha Tin; Tai Po
Status
Completed
Other Information