PWP No. 4236DS

Tai Po Sewage Treatment Works, Stage 5 Phase 2B

Project Scope
Expansion and modification of existing Tai Po sewage treatment works.
Major Improvements and Benefits
To increase the treatment capacity of Tai Po sewage treatment works to meet the need of existing and future development.
Consultants
Contractor
DC/2009/09 - China Harbour Engineering Company Limited
DE/2009/09 - The Jardine Engineering Corporation Limited
Contract No.
DC/2009/09, DE/2009/09, , ,
Project Commencement Date
29 January 2010
Project Completion Date
June 2014
Project estimate
About $660 million
Controlling Division
Sewerage Projects Division
Type
Sewerage and sewage treatment
District
Tai Po
Status
Completed