PWP No. 4185CD
Drainage improvement works at Yuen Long, stage 1
Project Scope
Construction of drainage channels and stormwater drains at Tai Tseng Wai, Shui Tsiu San Tsuen, Ho Lik Pui and Shan Ha Tsuen
Major Improvements and Benefits
Reduction of the flood risk by bringing the drainage system up to the current flood protection standard
Consultants
Atkins China Limited
Contractor
Ming Shing Construction Engineering Co. Ltd.
Contract No.
DC/2019/05
Project Commencement Date
29 October 2020
Project Completion Date
16 March 2023
Project estimate
About $256.2 million
Controlling Division
Project Management Division
Type
Flood Prevention
District
Yuen Long
Status
Completed