Newsletter Vol. 3
Enhancement Works for Kwun Tong Sewage Pumping Station
To cater for future development of East Kowloon, the Drainage Services Department (DSD) will enhance the Kwun Tong Sewage Pumping Station (KTSPS), which is situated near Kwun Tong Bypass and Wai Yip Street. The enhancement works have commenced in late 2017 and are scheduled for completion in end 2022. This newsletter provides the latest information on the progress of construction and related information of the project.
Construction Sequence of the Project
Item | Status |
---|---|
Enclosure of Site Area |
Completed |
Ground Investigation | Completed |
Diversion of Underground Utilities | Completed |
Construction of Piles and Foundation | In progress |
Construction of ELS and Excavation for Balancing Tank | In progress |
Construction of Balancing Tank and its Associated Facilities | |
Construction of Landscaped Deck | |
Installation of Ventilation System and Deodorization Facilities | |
Construction of the Connecting Roads and the Ancillary Works | |
Testing of Associated E&M Equipment | |
Beautification of Landscaped Deck and Installation of Playground Facilities | |
Testing & Commissioning |
Open to Public
What is Excavation and Lateral Support (ELS) System?
The photo above shows part of the ELS works.
The lateral support system could provide support to the soil adjacent to the excavated area, so that the underground facilities such as pile caps and basement can be constructed within the excavated area. The construction of lateral support system mainly includes:-
- Construction of king post & installation of sheet piles
- Installation of waling
- Grouting to prevent groundwater ingress if necessary
The ELS system we are setting up will be used for constructing the underground balancing tank with 12 meters depth. The whole ELS system requires about 9 months to a year for completion.
The construction of the lateral support system for balancing tank are in progress. The photo above shows the preparation works for the welding of sheet piles.
The photos above show the driving, welding and testing of sheet piles.
Engaging our Neighbours
The project team of DSD and the engineering consultants introduced the project to committee members of Save Our Urban Parks Alliance and the Chairman and Vice Chairman of Laguna City (Phase 1, 2 & 4) in early March 2019 and obtained their views towards the project.
Contact Us
Contract No. | DC/2017/05 |
---|---|
Contractor | Geo-Engineering Corporation |
Project Hotline | 6466 2466 |
pro@dc201705.com.hk | |
Consultant | Atkins China Limited |