The operation of our Department is funded by the General Revenue Account and the Capital Works Reserve Fund. Our Department's operating expenditure is met directly from the General Revenue Account which is the Government's main account and acts as the central funding device, while the Capital Works Reserve Fund was set up to finance public works programmes, acquisition of land, capital subventions and major systems and equipment items. To optimise the use of public funds, we always enhance our sewerage and stormwater drainage services in a cost-effective and environmentally responsible manner.

Departmental Operating Expenditure

In 2012-13, the total expenditure of our Department was about $1.9 billion. Of this allocation, salaries accounted for about $770 million, with the rest being contributed by departmental expenses and capital items.

A Summary for the past five years of our operating expenditure is highlighted below:

Summary of DSD Operating Expenditure for the Past Five Years 2008-09 2009-10 2010-11 2011-12 2012-13
($M)
Operating Expenditure (Total) 1,657.2 1,736.9 1,776.8 1,838.6 1,910.7
Recurrent Expenditure - Personal Emoluments 699.5 693.0 685.9 727.4 769.3
Recurrent Expenditure
- Departmental Expenses (including Mandatory Provident Fund & Civil Service Provident Fund)
957.3 1,035.9 1,083.8 1,111.2 1,141.4
Non-recurrent Expenditure 0.4 8.0 7.1 0.0 0.0

Summary of DSD Operating Expenditure in 2012-13

[section9_chart1.jpg]

Operating Expenditure (Total) is $1,910.7M, $769.3M (40.3%) of Recurrent Expenditure - Personal Emoluments , $1,141.4M (59.7%) of Recurrent Expenditure - Departmental Expenses(including Mandatory Provident Fund & Civil Service Provident Fund)

Capital Works Project Expenditure

In general, we have to conduct the Capital Works Resource Allocation Exercise annually to estimate the project expenses for all the capital works. We need to update and well document the cost estimate including cashflow of a project in all stages taking due account of the prevailing market rates and risk factors. Our Department also maintains a departmental committee for vetting the project estimates for inclusion in the LegCo Public Works Subcommittee papers and the vetting of pre-tender estimates of all works contracts, including term contracts. The cost estimate of a project will be closely monitored against the Approved Project Estimate and the administrative cap imposed by the Financial Services and the Treasury Bureau to ensure adequate funds for completing the approved works are available. In addition, we have a committee chaired by the Director to monitor the progress of all major capital works projects and to ensure that the funds allocated are effectively expended.

Value and Number of Drainage and Sewerage projects under planning, design and construction

  Unit 2008-09 2009-10 2010-11 2011-12 2012-13
Value of Drainage projects under planning,design and construction million of HK$ 13,330 13,373 12,707 14,323 11,288
Value of Sewerage projects under planning, design and construction million of HK$ 33,288 36,635 39,875 41,200 49,872
No. of drainage projects under planning, design and construction No. 34 29 24 22 20
No. of sewerage projects under planning, design and construction No. 55 58 70 70 77

Sewage Services Operating Accounts

The 'Sewage Services Charging Scheme' was introduced on 1 April 1995 according to the "Polluter Pays" Principle. All premises connected to public sewers are required to pay the sewage services charges. The charges were set to recover only the operating and maintenance costs of the public sewage facilities, while the capital costs of building these facilities will continue to be borne by the Government.

The revenue and expenditure in the Sewage Services Operating Accounts for the past five years are summarised in the Table below:

Summary of Sewage Services Operating Accounts for the Past Five Years 2008-09 2009-10 2010-11 2011-12 2012-13#
($M)
Sewage Charge Revenue 532 583 639 703 776
Trade Effluent Surcharge Revenue 189 192 201 204 207
Other Revenue 34 35 35 40 40
Overall Revenue 755 810 875 947 1,023
Expenditure (excluding depreciation) (1,273) (1,377) (1,402) (1,483) (1,538)
Depreciation (687) (698 ) (723 ) (751) (801)
Overall Expenditure (1,960) (2,075) (2,125) (2,234) (2,339)
(Deficit) (1,205) (1,265 ) (1,250 ) (1,287) (1,316)

Notes : # The 2012-13 figures are provisional. The final figures will be posted on our website after endorsement by the Sewage Services Accounts Committee.

Overall Revenue of Sewage Services Operating Accounts Breakdown in 2012-13

[section9_chart2.jpg]

Overall Revenue is $1,023M, $776M (75.9%) of Sewage Charge Revenue, $207M (20.2%) of Trade Effluent Surcharge Revenue, $40M (3.9%) of Other Revenue

Overall Revenue and Expenditure in the Sewage Services Operating Accounts

[section9_chart3.jpg]

2008-09 Overall Revenue was 755M and Overall Expenditure was 1960M, 2009-10 Overall Revenue was 810M and Overall Expenditure was 2075, 2010-11 Overall Revenue was 875 and Overall Expenditure was 2125, 2011-12 Overall Revenue was 947 and Overall Expenditure was 2234

Sewage Services Operating Cost Recovery Rates

The sewage services operating cost recovery rates for 2011-12 and 2012-13 are as follows:

  Total
2011-12 2012-13
Revenue of Sewage Charge and Trade Effluent Surcharge ($M) 907 983
Expenditure (excluding depreciation) of Sewage Charge and Trade Effluent Surcharge ($M) 1,443 1,498
Operating Cost Recovery Rate (%) 62.9 65.6

Notes :

  1. "Miscellaneous services" are excluded from the above calculation.
  2. Depreciation is at present not recovered through the Sewage Charge and Trade Effluent Surcharge.
  3. The 2012-13 revenue and expenditure are only provisional and are subject to endorsement by the Sewage Services Accounts Committee.

Adjustment of Sewage Services Charge

To enhance the "Polluter Pays" Principle and to encourage the public to conserve valuable water, the Legislative Council has approved a gradual increase of the sewage charge for 10 years starting from 1 April 2008. Since that day, the sewage charge rate was revised from the original $1.20 to $1.31 per cubic metre of water supplied. The rate is and then gradually increased by 9.3 per cent per annum until reaching $2.92 per cubic metre on 1 April 2017.

Sewage Charge Rate

[section9_chart4.jpg]

2008-09 charges $1.31/meter cube, 2009-10 charges $1.43/meter cube, 2010-11 charges $1.57/meter cube, 2011-12 charges $1.71/meter cube, 2012-13 charges $1.87/meter cube, 2013-14 charges $2.05/meter cube, 2014-15 charges $2.24/meter cube, 2015-16 charges $2.44/meter cube, 2016-17 charges $2.67/meter cube, From 2017 onwards charges $2.92/meter cube
Top

 

[Executive Summary] [Traditional Chinese Version] [Simplified Chinese Version] [Graphical Version] [Independent Assurance Opinion Statements] [Feedback] [Key Statistics and Data] [GRI Content Index] [Sitemap]

Home | Director's Statement | About the Report | The Year's Highlights | Governance Approach |
Our Core Responsibilities | Managing the Environment | Engaging the Community | Collaboration with Working Partners | Operation Efficiency | Caring Our Staff | Meeting the Targets |

(c) Copyright 2013 Best viewed by MS IE 8.0 or above with resolution 1024 x 768.