Major
Sewerage Projects
Harbour
Area Treatment Scheme (HATS), Stage I >>
Harbour
Area Treatment Scheme (HATS), Stage I |
Estimated Project Cost ($M) |
8,230 |
Aim:
Improve water quality in Victoria Harbour by collecting 70%
of all sewage generated from urban areas around Victoria Harbour
for centralized treatment
|
Start
Date |
Early
94 |
Scope:
Construct a 23.6 km deep tunnel system, a sewage treatment works
(STW) at Stonecutters Island and a 1.7-km submarine outfall
|
%
Completed |
90% |
Services
area: Kowloon peninsula, Kwai Chung, Tsing Yi, Tseung Kwan
O, Shau Kei Wan and Chai Wan
|
Completion
Date |
End
01 |
Progress:
The Stonecutters Islands STW and the outfall completed and in
operation since May 1997 and July 1999 respectively. Works on
the deep tunnel system are nearing completion for phased commissioning
towards end 2001.
|
|
Sewerage
Master Plan (SMP) Works>>
Tolo
Harbour SMP |
Estimated Project Cost ($M) |
931 |
Aim:
Improve water quality in Tolo Harbour
|
Start
Date |
Mid
93 |
Scope:
Provide public sewerage facilities to 169 unsewered areas in
Shatin and Tai Po
|
%
Completed |
26% |
Services
area: Shatin and Tai Po
|
Completion
Date |
2013 |
Progress:
Provision of public sewerage systems to 46 unsewered areas was
completed.
|
|
Hong
Kong Island South SMP |
Estimated Project Cost ($M) |
922 |
Aim:
Improve the sewerage system on Hong Kong Island South in order
to protect bathing beaches from pollution and to meet development
needs
|
Start
Date |
Mid
90 |
Scope:
Construct and improve 32 km of sewers, 17 pumping stations,
a sewage treatment plant at Shek O, an underground sewage treatment
plant at Stanley, and a 2.3 km long submarine outfall
|
%
Completed |
100% |
Services
area: Hong Kong Island South from Shouson Hill to Shek O
|
Completion
Date |
Early
00 |
Progress:
All works were completed.
|
|
Outlying
Islands SMP |
Estimated Project Cost ($M) |
1,397 |
Aim:
Collect sewage generated on Lantau Island, Lamma Island, Peng
Chau and Cheung Chau for proper treatment and disposal
|
Start
Date |
Early
98 |
Scope:
Construct and improve about 20 km of sewers, 4 pumping stations,
7 sewage treatment plants and 4 outfalls on Outlying Islands
under Stage 1 works. The Stage 2 works are under review.
|
%
Completed |
3% |
Services
area: Lantau Island, Lamma Island, Peng Chau and Cheung
Chau
|
Completion
Date |
2009 |
Progress:
For Lantau Island, the upgrading works at Mui Wo sewage treatment
plant were completed in May 2000 and the upgrading works at
Siu Ho Wan sewage treatment plant will commence in Mid 2001.
The sewerage works for Ngong Ping are at the EIA study and investigation/design
stage. The construction works will commence in end 2003. The
upgrading works at Cheung Chau sewage treatment plant commenced
in Sep 2000. The sewerage works for Peng Chau and Lamma Island
will commence in end 2002 and in mid 2003 respectively.
|
|
Port
Shelter SMP |
Estimated Project Cost ($M) |
569 |
Aim:
Improve water quality within the Port Shelter marine zone
|
Start
Date |
End
93 |
Scope:
Construct about 64 km of sewers, 23 pumping stations and 12
km of rising mains to collect sewage from 17 unsewered areas
in the Port Shelter catchment
|
%
Completed |
18% |
Services
area: Sai Kung, Pak Sha Wan and Silverstrand
|
Completion
Date |
2007 |
Progress:
Stage 1 works and part of stage 2 works were completed. Design
of stage 2 remaining works and stage 3 works is in progress
|
|
Tseung
Kwan O SMP |
Estimated Project Cost ($M) |
33 |
Aim:
Improve water quality in Tseung Kwan O
|
Start
Date |
2004 |
Scope:
Construct 5.5 km of sewers and 2 pumping stations to 9 unsewered
villages in Tseung Kwan O
|
%
Completed |
-- |
Services
area: Tseung Kwan O
|
Completion
Date |
2006 |
Progress:
Design of the works is in progress
|
|
North
District SMP |
Estimated
Project Cost ($M) |
1,142 |
Aim:
Provide sewerage facilities to unsewered areas in North District
and improve the sewerage system to meet development needs
|
Start
Date |
End
97 |
Scope:
Upgrade capacity and treatment level of Shek Wu Hui STW and
construct 16 km of trunk sewers, 25 pumping stations and provide
public sewers to 74 villages in North District
|
%
Completed |
30% |
Services
area: North District
|
Completion
Date |
2009 |
Progress:
About 3 km of trunk sewers along Sha Tau Kok Road were completed.
Upgrading Shek Wu Hui STW was completed
|
|
Yuen
Long & Kam Tin SMP |
Estimated
Project Cost ($M) |
2,871 |
Aim:
Improve water quality in Deep Bay and local watercourses and
provide new sewerage facilities to meet developments needs
|
Start
Date |
End
93 |
Scope:
Improve about 7 km of sewers in Yuen Long Town, construct 3km
of flow diversion sewer from Yuen Long STP to San Wai STP, construct
about 50 km of trunk sewers and provide public sewerage system
to 43 unsewered villages in NWNT, and expand the existing San
Wai STP |
%
Completed |
4% |
Services
area: NWNT
|
Completion
Date |
2008 |
Progress:
Improvement to Yuen Long Town sewers and flow diversion sewer
completed. Construction works for other trunk sewers in the
area are scheduled to start in October 2001. Design of the
remaining works is in progress.
|
|
Tuen
Mun SMP |
Estimated
Project Cost ($M) |
1,061 |
Aim:
Provide sewerage facilities to unsewered areas in Tuen Mun and
improve the sewerage system to meet development needs
|
Start
Date |
Mid
95 |
Scope:
Construct 2.2 km of trunk sewers, 6 pumping stations, 2 low-flow
interceptors, provide public sewers to 25 unsewered villages
in Tuen Mun, and upgrade Pillar Point STW
|
%
Completed |
8% |
Services
area: Tuen Mun
|
Completion
Date |
2010 |
Progress:
Construction of Ho Pong Street pumping station, Yuen Long-Tuen
Mun corridor trunk sewer, and Tuen Mun Road and Siu Hong Road
low-flow interceptors completed
|
|
Chai
Wan & Shau Kei Wan SMP |
Estimated
Project Cost ($M) |
25 |
Aim:
Improve the sewerage system in Chai Wan and Shau Kei Wan.
|
Start
Date |
Early
95 |
Scope:
Improve and construct 1.7 km of sewers in the areas
|
%
Completed |
100% |
Services
area: Chai Wan and Shau Kei Wan
|
Completion
Date |
End
97 |
Progress:
Works completed
|
|
Aberdeen,
Ap Lei Chau and Pokfulam SMP |
Estimated
Project Cost ($M) |
472 |
Aim:
Improve the sewerage system in Aberdeen, Ap Lei Chau and Pok
Fu Lam to meet development needs
|
Start
Date |
Mid
98 |
Scope:
Upgrade the existing Aberdeen Sewage Screening Plant, construct
3.4 km of trunk sewers from Wong Chuk Hang to the plant, improve
15.5 km of branch sewers, and rectify the expedient connections
in the areas
|
%
Completed |
45% |
Services
area: Aberdeen, Ap Lei Chau and Pok Fu Lam
|
Completion
Date |
2006 |
Progress:
Installation of trunk sewer by pipe jacking method was completed.
Construction of branch sewers and pumping station is in progress
|
|
Central,
Western & Wan Chai West SMP |
Estimated
Project Cost ($M) |
2,589 |
Aim:
Improve the sewerage system in Central, Western and Wan Chai
to meet development needs and rectify improper connections in
the catchment area
|
Start
Date |
End
96 |
Scope:
Construct 5.6 km of trunk sewers, 35 km of reticulation sewers
and 2 new pumping stations at Wan Chai and Central
|
%
Completed |
55% |
Services
area: Central, Western and Wan Chai |
Completion
Date |
2006 |
Progress:
Trunk sewer works under stage 1 were completed. The stage
2 phase 1 works have started in October 2001
|
|
Wan
Chai East & North Point SMP |
Estimated
Project Cost ($M) |
1,876 |
Aim:
Improve the sewerage system in Wan Chai East and North Point
|
Start
Date |
Early
98 |
Scope:
Construct and improve 16.8 km of sewers and a new pumping station
in the North Point Sewage Screening Plant
|
%
Completed |
6% |
Services
area: Wan Chai East and North Point
|
Completion
Date |
2006 |
Progress:
About 3.5 km of sewers completed
|
|
Tsuen
Wan, Kwai Chung & Tsing Yi SMP |
Estimated
Project Cost ($M) |
1,225 |
Aim:
Improve the sewerage system in Tsuen Wan, Kwai Chung and Tsing
Yi and to provide a new sewerage system in Ting Kau, Sham Tseng
and Tsing Lung Tau to meet development needs
|
Start
Date |
End
94 |
Scope:
Construct and improve 14.2 km of sewers, an industrial wastewater
pumping station, and rectify expedient connections in the industrial
areas in Tsuen Wan, Kwai Chung and Tsing Yi; construct a sewage
treatment plant, a submarine outfall, 8 km of trunk sewers,
7 km of branch sewers to villages in Ting Kau, Sham Tseng and
Tsing Lung Tau
|
%
Completed |
-- |
Services
area: Tsuen Wan, Kwai Chung, Tsing Yi, Ting Kau, Sham Tseng
and Tsing Lung Tau
|
Completion
Date |
2005 |
Progress:
Sewer improvement, industrial wastewater pumping station and
rectification of expedient connections in industrial areas
in Tsuen Wan, Kwai Chung and Tsing Yi completed. Reclamation
for Sham Tseng sewage treatment plant, and construction of
1 km of trunk sewers and 2 km of branch sewers were completed
|
|
East
West Kowloon SMP |
Estimated
Project Cost ($M) |
868 |
Aim:
Improve the sewerage system in San Po Kong, Kowloon Bay and
Kwun Tong in order to improve water quality of neighboring waters
|
Start
Date |
Mid
91 |
Scope:
Construct and improve 17.3 km of sewers, 7 dry weather flow
interceptors and rectify expedient connections in industrial
areas in San Po Kong, Kowloon Bay and Kwun Tong
|
%
Completed |
100% |
Services
area: San Po Kong, Kowloon Bay and Kwun Tong
|
Completion
Date |
End
01 |
Progress:
Works substantially completed
|
|
North
West Kowloon SMP |
Estimated
Project Cost ($M) |
978 |
Aim:
Improve the sewerage system in Sham Shui Po, Mong Kok and Yau
Ma Tei so as to improve the water quality of the receiving waters
|
Start
Date |
End
92 |
Scope:
Construct and improve 24.4 km of sewers, 2 pumping stations,
13 dry weather flow interceptors and rectify expedient connections
in industrial areas in Sham Shui Po, Mong Kok and Yau Ma Tei
|
%
Completed |
60% |
Services
area: Sham Shui Po, Mong Kok and Yau Ma Tei
|
Completion
Date |
Early
03 |
Progress:
About 60% of the works already completed
|
|
North
& South Kowloon SMP |
Estimated
Project Cost ($M) |
1,030 |
Aim:
Improve the sewerage system in Tsim Sha Tsui, Hung Hom Bay reclamation,
Hung Hom, To Kwa Wan and Wong Tai Sin so as to improve the water
quality of the receiving waters
|
Start
Date |
Early
95 |
Scope:
Construct and improve 11.6 km of sewers, 2 pumping stations,
8 dry weather flow interceptors and expand an existing pumping
station in Tsim Sha Tsui, Hung Hom Bay reclamation, Hung Hom,
To Kwa Wan and Wong Tai Sin
|
%
Completed |
70% |
Services
area: Tsim Sha Tsui, Hung Hom Bay reclamation, Hung Hom,
To Kwa Wan and Wong Tai Sin
|
Completion
Date |
End
07 |
Progress:
All Stage I works substantially completed
|
|
Other
Major Sewerage Projects>>
Tolo
Harbour Effluent Export Scheme (THEES) |
Estimated
Project Cost ($M) |
910 |
Aim:
Remove nutrient and improve water quality in Tolo Harbour
|
Start
Date |
Mid
90 |
Scope:
Export treated effluent from Tai Po and Shatin STWs to Victoria
Harbour via pipelines and tunnel
|
%
Completed |
100% |
Services
area: Shatin and Tai Po
|
Completion
Date |
End
96 |
Progress:
Effluent export scheme fully operational
|
|
Tai
Po Sewage Treatment Works - Stage V |
Estimated
Project Cost ($M) |
756 |
Aim:
Improve water quality in Tolo Harbour
|
Start
Date |
Early
04 |
Scope:
Stage V development of Tai Po STW
|
%
Completed |
-- |
Services
area: Tai Po
|
Completion
Date |
2010 |
Progress:
Design of Tai Po STW Stage V in progress
|
|
Improve
sewage treatment facilities on Hei Ling Chau, at Sha Tsui Detention
Centre on Lantau Island and at O Pui Shan Boy's Home |
Estimated
Project Cost ($M) |
230 |
Aim:
Improve water quality in Southern waters
|
Start
Date |
End
00 |
Scope:
Improve sewage treatment facilities on Hei Ling Chau, at Sha
Tsui Detention Centre on Lantau Island and at O Pui Shan Boy's
Home |
%
Completed |
90% |
Services
area: Hei Ling Chau and southern Lantau Island
|
Completion
Date |
End
01 |
Progress:
The works will substantially be completed in end 2001
|
|
Sai
Kung Sewage Treatment Works - Phase 2 Ungrading |
Estimated
Project Cost ($M) |
300 |
Aim:
Improve water quality in Port Shelter
|
Start
Date |
2004 |
Scope:
Upgrade Sai Kung STW |
%
Completed |
-- |
Services
area: Sai Kung area
|
Completion
Date |
2007 |
Progress:
EIA study and design are in progress
|
|
Shatin
Sewage Treatment Works - Stage III Extension |
Estimated
Project Cost ($M) |
1,847 |
Aim:
Improve water quality in Tolo Harbour
|
Start
Date |
Early
01 |
Scope:
Stage III extension of Shatin STW |
%
Completed |
-- |
Services
area: Shatin and Ma On Shan
|
Completion
Date |
End
07 |
Progress:
The works were commenced in Feb 2001
|
|
|