Major
Flood Control Projects
Completed
Projects>>
Table
A1.1 |
Major
Flood Control Projects in Northwestern NT( Completed Projects) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
7035CD
|
Village
flood protection for the San Tin villages and Chau Tau Tsuen, North
West New Territories
|
232
|
End
96
|
Early
00
|
Phase
1 Village Flood Protection Works for San Tin
|
End
96
|
End
99
|
Phase
2 Village Flood Protection Works for Chau Tau
|
Mid
97
|
End
99
|
7043CD
|
North
West New Territories development main drainage channels for
Yuen Long and Kam Tin stage I phase 2
|
349
|
End
95
|
Mid
99
|
7060CD
|
North
West New Territories development main drainage channels for
Yuen Long and Kam Tin, stage I phase 1
|
557
|
End
93
|
Mid
99
|
7071CD
|
Village
flood protection for Sha Po Tsuen, Kam Tin, New Territories
|
75
|
End
96
|
Early
00
|
7473CD
|
Tin
Shui Wai development village flood protection works for Ha
Mei San Tsuen
|
37
|
Mid
97
|
End
98
|
Table
A1.2 |
Major
Flood Control Projects in Northern NT - including Shenzhen River Regulation
Project (Completed Projects) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
7072CD
|
Village
flood protection for Tsung Pak Long and Tai Tau Leng, New Territories
|
99
|
Early
96
|
End
98
|
7094CD
|
River
training works for the Lower River Indus and River Beas
|
255
|
Early
99
|
End
01
|
7651CL
|
Formation
and servicing of Area 36, Fanling, phase 1
|
38
|
Early
99
|
Mid
01
|
4024CD
|
Shenzhen
River Regulation Project, stage I improvement to river bends
at Lok Ma Chau and Liu Pok
|
150
(300)
|
Mid
95
|
Early
97
|
4031CD
|
Regulation
of Shenzhen River, stage II, phase II improvement to river
sections between Liu Pok and Lok Ma Chau and from Lok Ma Chau to estuary
|
343
(697)
|
Mid
97
|
Mid
00
|
4044CD
|
Regulation
of Shenzhen River, stage II, phase I reprovisioning of border
road between Lok Ma Chau and Tam Kon Chau
|
126
(145)
|
End
96
|
End
98
|
Note : Costs quoted
are those shared by Hong Kong side; total construction cost in ()
Projects
in Progress>>
Table
A2.1 |
Major
Flood Control Projects in Northwestern NT (Projects in Progress) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
4114CD
|
Yuen
Long, Kam Tin, Ngau Tam Mei and Tin Shui Wai drainage improvements,
stage 1, phase 1 Yuen Long and Tin Shui Wai
|
208
|
End
01
|
Mid
05
|
4101CD
|
Rural
Drainage Rehabilitation Scheme, stage 2, phase 1 Nam Hang
drainage improvement
|
16
|
Mid
00
|
Mid
02
|
7029CD
|
Main
drainage channels for Ngau Tam Mei phase 2 Ngau Tam Mei to
Yau Mei San Tsuen section
|
132
|
Early
00
|
End
02
|
7081CD
|
Main
drainage channels for Yuen Long and Kam Tin, stage 2 remainder
|
289
|
Mid
01
|
End
03
|
7095CD
|
Main
drainage channels for Yuen Long and Kam Tin stage 2 Kam Tin
San Tsuen to Wang Toi Shan section
|
325
|
Mid
99
|
End
02
|
7097CD
|
Main
drainage channels for Yuen Long and Kam Tin stage 2 Kam Tin
Road to Tai Kek section
|
234
|
Mid
99
|
Early
02
|
7098CD
|
Phase
1 village flood protection for Pok Wai and Wang Chau, North West
New Territories
|
92
|
End
99
|
Mid
02
|
7100CD
|
Main
drainage channel for Ngau Tam Mei phase 1 Yau Mei San Tsuen
to Tai Sang Wai section
|
366
|
End
99
|
Early
03
|
7107CD
|
Village
flood protection for Chuk Yuen Tsuen and Ha San Wai, North West
New Territories
|
122
|
End
00
|
Mid
03
|
7113CD
|
Main
drainage channels for Yuen Long and Kam Tin Sham Chung Channel
|
93
|
Early
01
|
Early
03
|
Table
A2.2 |
Major
Flood Control Projects in Northern NT (Projects in Progress) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
4091CD
|
Rural
Drainage Rehabilitation Scheme, stage 1, phase 1A rehabilitation
works at River Indus
|
144
|
End
98
|
End
01
|
4093CD
|
Rural Drainage
Rehabilitation Scheme, stage 1, phase 1B rehabilitation works
at River Beas
|
134
|
Early
99
|
End
01
|
7053CL
|
River
training works for the Upper River Indus
|
585
|
Mid
99
|
End
03
|
7087CD
|
Shek
Wu Hui development, package 4, engineering works
|
265
|
End
98
|
Early
02
|
Table
A2.3 |
Major
Flood Control Projects in West Kowloon (Projects in Progress) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
4089CD
|
West
Kowloon drainage improvement, stage 1 works
|
462
|
Early
98
|
Early
03
|
4099CD
|
West
Kowloon drainage improvement, stages 2 phase 1 works
|
1264
|
End
99
|
End
04
|
4106CD
|
West
Kowloon drainage improvement, stage 2 phase 2 and stage 3 phase 1
works
|
1733
|
Early
01
|
Mid
07
|
Projects
under Planning>>
Table
A3.1 |
Major
Flood Control Projects in Northwestern NT (Projects under Planning) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
4064CD
|
Rural
drainage rehabilitation scheme NWNT
|
80
|
Early
03
|
Mid
05
|
4102CD
|
Drainage
improvement in Tuen Mun and Sham Tseng
|
77
|
End
02
|
End
07
|
7022CD
|
Main
drainage channels for Yuen Long and Kam Tin Tin Tsuen Channels
|
100
|
Mid
03
|
Early
05
|
7030CD
|
Village
flood protection for Yuen Long, Kam Tin and Ngau Tam Mei, North
West New Territories, stage 1 remainder
|
135
|
End
01
|
End
04
|
7070CD
|
Yuen
Long Bypass floodway
|
494
|
End
02
|
End
05
|
7073CD
|
Main
drainage channels and poldered village protection schemes for San
Tin, NWNT Phase 3, Part 1 eastern main drainage channel for
San Tin
|
360
|
End
02
|
End
05
|
7074CD
|
Village
flood protection for Yuen Long, Kam Tin and Ngau Tam Mei NWNT
stage II
|
Mai Po
Lo Wai/Mai Po San Tsuen, Ma Tin Tsuen and Shui Pin Wai
|
Remainder
Villages Shui Pin Tsuen, Tai Kiu and other local drainage
works
|
|
|
|
|
7227CL
|
Tin
Shui Wai development village flood protection works for Sheung
Cheung Wai
|
22
|
End
02
|
Mid
05
|
Table
A3.2 |
Major
Flood Control Projects in NT (Projects under Planning) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
4064CD
|
Rural
drainage rehabilitation scheme - River Ganges
|
118
|
Early
03
|
Mid
05
|
4112CD
|
Drainage
improvement in Northern New Territories - package A
|
686
|
Mid
04
|
End
08
|
4090CD
|
Regulation
of Shenzhen River, stage III
|
559
(935)
|
End
01
|
Mid
05
|
Table
A3.3 |
Major
Flood Control Projects in West Kowloon (Project under Planning) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
4059CD
|
West
Kowloon drainage improvement, stage 3 phase 2
|
580
|
End
03
|
End
07
|
4108CD
|
West
Kowloon drainage improvement Lai Chi Kok Transfer Scheme
|
762
|
End
06
|
Mid
10
|
Table
A3.4 |
Other
Drainage Projects (Project under Planning) |
PWP
No.
|
Title
|
Estimated
Construction Cost ($M)
|
Start
Date
|
Completion
Date
|
4103CD
|
Drainage improvement
in Northern Hong Kong Island Hong Kong West drainage tunnel
|
1689
|
End
06
|
End
10
|
4104CD
|
Drainage
improvement in Northern Hong Kong Island Lower catchment
improvement
|
177
|
Mid
02
|
Early
12
|
4109CD
|
Drainage
improvement in Shatin and Tai Po
|
418
|
Early
04
|
End
07
|
4110CD
|
Drainage
improvement in Tsuen Wan, Kwai Chung and Tsing Yi urban drainage
improvement works
|
70
|
Mid
02
|
Mid
05
|
4111CD
|
Drainage
improvement in Tsuen Wan, Kwai Chung and Tsing Yi Tsuen Wan
drainage tunnel
|
1094
|
Mid
02
|
End
11
|
|