Working Plan & Arrangements

Advance Works (under DC/2010/07)

Construction of access manhole at Wong Nai Chung Road Open Car Park (completed in August 2012)

Phase 1 Construction (under DC/2012/03)

  • Construction of the following facilities: (commissioned in March 2015)
    • Phase 1 underground stormwater storage tank with a storage capacity of 30,000m3
    • Twin-cell Box Culvert
    • Movable Weir
    • Pump House and Fan Room
  • Re-provision of sports pitches
    • Pitch No. 3 and 4 (completed in August 2015)
    • Pitch No. 2 (completed in February 2016)

Phase 2 Construction (under DC/2012/03)

  • Construction of Phase 2 underground stormwater storage tank with a storage capacity of 30,000m3 (commissioned in March 2017)
  • Re-provision of Pitch No. 1 and 8 (completed in October 2017)