Major Sewerage Projects

 

Harbour Area Treatment Scheme (HATS), Stage I

Harbour Area Treatment Scheme (HATS), Stage I
Aim : Improve water quality in Victoria Harbour by collecting 70% of sewage generated from urban areas around Victoria Harbour for centralized treatment
Scope: Construct a 23.6 km deep tunnel system, a sewage treatment works (STW) at Stonecutters Island and a 1.7-km submarine outfall
Services area: Kowloon peninsula, Kwai Chung, Tsing Yi, Tseung Kwan O, Shau Kei Wan and Chai Wan
Progress: The Stonecutters Islands STW and the outfall completed and in operation since May 1997 and July 1999 respectively. The Stage I works have been fully commissioned in Dec 2001 and the system is now treating 1.3 million cu. m. of sewage everyday
Project Cost ($M) 8,230 % Completed 100%
Start Date Early 1994 Completion End 2001
 

Sewerage Master Plan (SMP) Works

Hong Kong Island South SMP
Aim : Improve the sewerage system on Hong Kong Island South in order to protect bathing beaches from pollution and to meet development needs
Scope: Construct and improve 32 km of sewers, 17 pumping stations, a sewage treatment plant at Shek O, an underground sewage treatment plant at Stanley, and a 2.3 km long submarine outfall
Services area: Hong Kong Island South from Shouson Hill to Shek O
Progress: All works were completed
Project Cost ($M) 922 % Completed 100%
Start Date Mid 1990 Completion Early 2000

 

Chai Wan & Shau Kei Wan SMP
Aim : Improve the sewerage system in Chai Wan and Shau Kei Wan
Scope: Improve and construct 1.7 km of sewers in the areas
Services area: Chai Wan and Shau Kei Wan
Progress: Works completed
Project Cost ($M) 25 % Completed 100%
Start Date Early 1995 Completion End 1997

 

East Kowloon SMP
Aim : Improve the sewerage system in San Po Kong, Kowloon Bay and Kwun Tong in order to improve water quality of neighboring waters
Scope: Construct and improve 17.3 km of sewers, 7 dry weather flow interceptors and rectify expedient connections in industrial areas in San Po Kong, Kowloon Bay and Kwun Tong
Services area: San Po Kong, Kowloon Bay and Kwun Tong
Progress: Works substantially completed
Project Cost ($M) 868 % Completed 100%
Start Date Mid 1991 Completion End 2001

 

North West Kowloon SMP
Aim : Improve the sewerage system in Sham Shui Po, Mong Kok and Yau Ma Tei so as to improve the water quality of the receiving waters
Scope: Construct and improve 24.4 km of sewers, 2 pumping stations, 13 dry weather flow interceptors and rectify expedient connections in industrial areas in Sham Shui Po, Mong Kok and Yau Ma Tei
Services area: Sham Shui Po, Mong Kok and Yau Ma Tei
Progress: About 90% of the works already completed
Project Cost ($M) 978 % Completed 90%
Start Date End 1992 Completion Early 2003

 

Tolo Harbour SMP
Aim : Improve water quality in Tolo Harbour
Scope: Provide public sewerage facilities to 169 unsewered areas in Shatin and Tai Po
Services area: Shatin and Tai Po
Progress: Provision of public sewerage systems to 46 unsewered areas was completed. Construction of public sewerage facilities for another 27 unsewered areas is in progress
Project Cost ($M) 931 % Completed 26%
Start Date Mid 1993 Completion 2013

 

Outlying Islands SMP
Aim : Collect sewage generated on Lantau Island, Lamma Island, Peng Chau and Cheung Chau for proper treatment and disposal
Scope: Construct and improve about 20 km of sewers, 4 pumping stations, 7 sewage treatment plants and 4 outfalls on Outlying Islands under Stage 1 works
Services area: Lantau Island, Lamma Island, Peng Chau and Cheung Chau
Progress: For Lantau Island, the upgrading works at Mui Wo sewage treatment plant were completed in May 2000 and the upgrading works at Siu Ho Wan sewage treatment plant commenced in Mid 2001. The sewerage works for Ngong Ping are at the EIA study and investigation/design stage. The construction works will commence in end 2003. The upgrading works at Cheung Chau sewage treatment plant commenced in Sep 2000. The sewerage works for Peng Chau will commence in end 2002. The review on Stage 2 works has just been completed
Project Cost ($M) 1,397 % Completed 3%
Start Date Early 1998 Completion -

 

Port Shelter SMP
Aim : Improve water quality within the Port Shelter water control zone
Scope: Construct about 64 km of sewers, 23 pumping stations and 12 km of rising mains to collect sewage from 17 unsewered areas in the Port Shelter catchment
Services area: Sai Kung, Pak Sha Wan and Silverstrand
Progress: Stage 1 works and part of Stage 2 works were completed, covering about 13 km of sewers, 6 pumping stations and 2 km of rising mains. Design of Stage 2 remaining works and Stage 3 works is in progress
Project Cost ($M) 569 % Completed 21%
Start Date End 1993 Completion 2008

 

North District SMP
Aim : Provide sewerage facilities to unsewered areas in North District and improve the sewerage system to meet development needs
Scope: Upgrade capacity and treatment level of Shek Wu Hui STW and construct 16 km of trunk sewers, 25 pumping stations and provide public sewers to 74 villages in North District
Services area: North District
Progress: Upgrading Shek Wu Hui STW was completed. About 3 km of trunk sewers along Sha Tau Kok Road were completed. About 0.6 km of trunk sewers and 2 pumping stations along Castle Peak Road were completed. Construction of sewers for 4 unsewered areas is in progress
Project Cost ($M) 1,120 % Completed 35%
Start Date End 1997 Completion 2010

 

Yuen Long & Kam Tin SMP
Aim : Improve water quality in Deep Bay and local watercourses and provide new sewerage facilities to meet developments needs
Scope: Improve about 7 km of sewers in Yuen Long Town, construct 3 km of flow diversion sewer from Yuen Long STP to San Wai STP, construct about 50 km of trunk sewers and provide public sewerage system to 43 unsewered villages in NWNT, and expand the existing San Wai STP
Services area: NWNT
Progress: Improvement to Yuen Long Town sewers and flow diversion sewer completed. Construction works for the trunk sewers in the Yuen Long East started in July 2001 while that in the Yuen Long south will start in end 2002. Design of the remaining works is in progress
Project Cost ($M) 2,793 % Completed 4%
Start Date End 1993 Completion -

 

Tuen Mun SMP
Aim : Provide sewerage facilities to unsewered areas in Tuen Mun and improve the sewerage system to meet development needs
Scope: Construct 2.2 km of trunk sewers, 6 pumping stations, 2 low-flow interceptors, provide public sewers to 25 unsewered villages in Tuen Mun, and upgrade Pillar Point STW
Services area: Tuen Mun
Progress: Construction of Ho Pong Street pumping station, Yuen Long-Tuen Mun corridor trunk sewer, and Tuen Mun Road and Siu Hong Road low-flow interceptors completed
Project Cost ($M) 1,061 % Completed 8%
Start Date Mid 1995 Completion -

 

Aberdeen, Ap Lei Chau and Pokfulam SMP
Aim : Improve the sewerage system in Aberdeen, Ap Lei Chau and Pok Fu Lam to meet development needs
Scope: Upgrade the existing Aberdeen Sewage Screening Plant, construct 3.4 km of trunk sewers from Wong Chuk Hang to the plant, improve 15.5 km of branch sewers, and rectify the expedient connections in the areas
Services area: Aberdeen, Ap Lei Chau and Pok Fu Lam
Progress: Installation of trunk sewer by pipe jacking method was completed. Construction of branch sewers and pumping station is in progress. Detailed design of Stage 2 works is in progress
Project Cost ($M) 472 % Completed 80%
Start Date Mid 1998 Completion 2007

 

Central, Western & Wan Chai West SMP
Aim : Improve the sewerage system in Central, Western and Wan Chai West to meet development needs and rectify improper connections in the catchment area
Scope: Construct 5.6 km of trunk sewers, 35 km of reticulation sewers and 2 new pumping stations at Wan Chai and Central
Services area: Central, Western and Wan Chai West
Progress: Trunk sewer works under Stage 1 were completed. The Stage 2 phase 1 works have started in October 2001
Project Cost ($M) 2,589 % Completed 60%
Start Date End 1996 Completion 2007

 

Wan Chai East & North Point SMP
Aim : Improve the sewerage system in Wan Chai East and North Point
Scope: Construct and improve 16.8 km of sewers and a new pumping station in the North Point Sewage Screening Plant
Services area: Wan Chai East and North Point
Progress: About 3.5 km of sewers completed
Project Cost ($M) 1,876 % Completed 10%
Start Date Early 1998 Completion -

 

Tsuen Wan, Kwai Chung & Tsing Yi SMP
Aim : Improve the sewerage system in Tsuen Wan, Kwai Chung and Tsing Yi and to provide a new sewerage system in Ting Kau, Sham Tseng and Tsing Lung Tau to meet development needs
Scope: Construct and improve 14.2 km of sewers, an industrial wastewater pumping station, and rectify expedient connections in the industrial areas in Tsuen Wan, Kwai Chung and Tsing Yi; construct a sewage treatment plant, a submarine outfall, 8 km of trunk sewers and 7 km of branch sewers to villages in Ting Kau, Sham Tseng and Tsing Lung Tau
Services area: Tsuen Wan, Kwai Chung, Tsing Yi, Ting Kau, Sham Tseng and Tsing Lung Tau
Progress: Sewer improvement, industrial wastewater pumping station and rectification of expedient connections in industrial areas in Tsuen Wan, Kwai Chung and Tsing Yi completed. Reclamation for Sham Tseng sewage treatment plant, and construction of 2 km of trunk sewers and 3.5 km of branch sewers were completed. Construction of the Sham Tseng sewage treatment plant commenced in mid 2001
Project Cost ($M) 1,225 % Completed 52%
Start Date End 1994 Completion 2006

 

North & South Kowloon SMP
Aim : Improve the sewerage system in Tsim Sha Tsui, Hung Hom Bay reclamation, Hung Hom, To Kwa Wan and Wong Tai Sin so as to improve the water quality of the receiving waters
Scope: Construct and improve 11.6 km of sewers, 2 pumping stations, 8 dry weather flow interceptors and expand an existing pumping station in Tsim Sha Tsui, Hung Hom Bay reclamation, Hung Hom, To Kwa Wan and Wong Tai Sin
Services area: Tsim Sha Tsui, Hung Hom Bay reclamation, Hung Hom, To Kwa Wan and Wong Tai Sin
Progress: All Stage I works substantially completed. Design of Stage 2 works started in end 2001
Project Cost ($M) 1,030 % Completed 70%
Start Date Early 1995 Completion 2009

 

Tseung Kwan O SMP
Aim : Improve water quality in Tseung Kwan O
Scope: Construct 5.5 km of sewers and 2 pumping stations to 9 unsewered villages in Tseung Kwan O
Services area: Tseung Kwan O
Progress: Design of the works is in progress
Project Cost ($M) 33 % Completed -
Start Date 2005 Completion 2007
 

Other Major Sewerage Projects

Tolo Harbour Effluent Export Scheme (THEES)
Aim : Remove nutrient and improve water quality in Tolo Harbour
Scope: Export treated effluent from Tai Po and Shatin STWs to Victoria Harbour via pipelines and tunnel
Services area: Shatin and Tai Po
Progress: Effluent export scheme fully operational
Project Cost ($M) 910 % Completed 100%
Start Date Mid 1990 Completion End 1996

 

Improve sewage treatment facilities on Hei Ling Chau and at Sha Tsui Detention Centre on Lantau Island
Aim : Improve water quality in Southern waters
Scope: Improve sewage treatment facilities on Hei Ling Chau and at Sha Tsui Detention Centre on Lantau Island
Services area: Hei Ling Chau and southern Lantau Island
Progress: The works were substantially completed in Mar 2002
Project Cost ($M) 196 % Completed 100%
Start Date End 2000 Completion Early 2002

 

Shatin Sewage Treatment Works - Stage III Extension
Aim : Improve water quality in Tolo Harbour
Scope: Stage III extension of Shatin STW
Services area: Shatin and Ma On Shan
Progress: Phase 1 works commenced in Feb 2001. Phase 2 works commenced in Mar 2002
Project Cost ($M) 1,847 % Completed 12%
Start Date Early 2001 Completion End 2007

 

Tai Po Sewage Treatment Works - Stage V
Aim : Improve water quality in Tolo Harbour
Scope: Stage V development of Tai Po STW
Services area: Tai Po
Progress: Design of Tai Po STW Stage V in progress
Project Cost ($M) 756 % Completed 4%
Start Date Early 2004 Completion -