5.      CONCLUSIONS

5.1         The baseline water quality monitoring was conducted at 42 monitoring stations on 22 November 2014, 13 December 2014 and 24 January 2015. The monitoring results were used to establish the Action and Limit Levels for the relevant parameters during impact monitoring and also post-project monitoring throughout the implementation of the temporary sewage bypass works.

5.2         The baseline water quality monitoring was conducted at 42 monitoring stations, no marine construction works and observable pollution source were identified in the vicinity at the stations.