TABLE OF CONTENTS
2.4 Monitoring Parameters,
Frequency and Duration
3.4 Monitoring Parameters,
Frequency and Duration
List of Tables
Table 2.1 Air Quality Monitoring
Equipment
Table 2.2 Locations of Baseline Air
Monitoring Stations
Table 2.3 Air Quality Monitoring
Parameters, Frequency and Duration
Table 2.4 Summary of 1-hour TSP
Baseline Monitoring Results
Table 2.5 Summary of 24-hour TSP
Baseline Monitoring Results
Table 2.6 Derivation of Action and
Limit Levels for Air Quality
Table 2.7 Action and Limit Levels
for Air Quality
Table 3.1 Noise Monitoring
Equipment
Table 3.2 Locations of Baseline
Noise Monitoring Station
Table 3.3 Noise Monitoring
Parameters, Frequency and Duration
Table 3.4 Summary of Baseline Noise
Monitoring Results
Table 3.7 Criteria for Action and Limit Levels for Construction
Noise
Table 3.8 Action and Limit Levels for Construction Noise of the
Project
Figures
Figure 2.1 Locations
of Air Quality Monitoring Stations During Baseline Monitoring
Figure 3.1 Location
of Noise Monitoring Stations During Baseline Monitoring
List of Appendix
Appendix A Calibration Certificates of Monitoring Equipments
Appendix B Baseline Air Quality Monitoring Results
Appendix C Baseline Noise Monitoring Results
The
proposed construction of interconnection tunnel and diaphragm wall for main
pumping station at Stonecutters Island Sewage Treatment Works (SCISTW) (the
Project) is a Designated Project under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) and is governed by an
Environmental Permit (EP-322/2008/B). The Project comprises the construction of
Interconnection Tunnel between the Inlet Chamber of the Main Pumping Station
and the existing Riser Shaft and diaphragm wall for the Main Pumping Station
In accordance with the Environmental
Monitoring and Audit Manual (EM&A Manual) of the Project, baseline
monitoring of air quality and noise is required prior to commencement of
construction of the Project. As accesses to some of
the proposed monitoring stations as stipulated in the EM&A manual have been
rejected by other parties or found to be not available or not suitable, a
Monitoring Proposal, presenting the alternative monitoring stations,
requirements and methodologies for the monitoring, was submitted.
This
report documents the baseline monitoring of air quality at 1 monitoring station
and noise monitoring at 1 monitoring station as described in the Monitoring
Proposal. For monitoring station at Block A of Government Dockyard mentioned in
the Monitoring Proposal, as monitoring station will be established by the
Contract DE/2009/02 (Provision of Covers and Deodourisation Facilities to the
Existing Sedimentation Tanks at SCISTW), so baseline monitoring details at this
station are not mentioned in this report.
The
baseline monitoring of both air quality and noise was carried out between 23
November 2009 and 6 December 2009. Air quality was recorded in terms of 1-hour
Total Suspended Particulates (TSP) and 24-hour TSP. The weather during the
monitoring period was mainly sunny. For baseline noise levels, Leq(30-minute)
were recorded for non-restricted Restricted Hours (07:00 ¡V 19:00 on normal weekdays) and Leq(5-minute)
were recorded for restricted Restricted Hours (19:00 ¡V 23:00 and 23:00 ¡V 07:00 of next day
on normal weekdays, whole day on General Holidays and Sundays).
The averaged 1-hour TSP levels and 24-hour TSP levels at AM7 are summarized as follows:
Air quality monitoring
location |
AM7 |
Averaged 1-hr TSP (£gg/m3) |
110 |
Averaged 24-hr TSP (£gg/m3) |
119 |
The averaged baseline
noise levels are summarized in the following table:
Noise monitoring location |
NM6 |
Averaged baseline noise level during daytime on normal weekdays (Leq(30
min), dB(A)) |
76.5 |
Averaged baseline noise level during evening on normal weekdays (Leq(5 min),
dB(A)) |
60.4 |
Averaged baseline noise level during daytime and evening on General Holidays and Sundays (Leq(5 min),
dB(A)) |
61.5 |
Averaged baseline noise level during night-time on all days (Leq(5 min),
dB(A)) |
59.6 |
1.1.1.
China State - Shanghai Tunnel Joint Venture was
awarded the Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage
1.1.2.
The Project is a designated project and is governed
by an Environmental Permit (EP-322/2008/B).
1.1.3.
The scope of the Project comprises mainly:
n |
l Construction of Interconnection
Tunnel with concrete lining between the Inlet Chamber of the Main Pumping
Station and the existing Riser Shaft; l Construction of diaphragm wall, base
slab and pile cap for the Main Pumping Station and its Inlet Chamber; l Excavation within the diaphragm walls
for the Main Pumping Station and its
Inlet Chamber to founding levels; l Piling works for the Main Pumping
Stations; l Utilities upgrading and diversion
works; l Temporary launching shaft to be
handed over to MPS Contractor; l Carrying out ground monitoring and
instrumentation works; l Carrying out pumping test; l Miscellaneous building, civil and
electrical and mechanical works; and l Landscape works. |
1.1.4.
In accordance with the EM&A Manual of the
Project, environmental baseline conditions were established by the ET prior to
the commencement of construction of the Project.
1.1.5.
As accesses to some of
the proposed monitoring stations as stipulated in the EM&A manual have been
rejected by other parties or found to be not available or not suitable, a
Monitoring Proposal, presenting the alternative monitoring stations,
requirements and methodologies for the monitoring, was submitted.
1.1.6.
Baseline
monitoring was undertaken and baseline monitoring report was prepared prior to
commencement of construction of the Project.
1.2.
Purpose of the
Baseline Monitoring Report
1.2.1.
The purpose of this report is to review the
baseline conditions of the Project site and to establish baseline levels for
air and noise in accordance with the EM&A Manual and Monitoring Proposal.
These levels would be used as the basis for assessing environmental impact and
compliance during construction of the Project.
1.2.2.
This baseline monitoring
report presents the baseline monitoring requirements, methodologies and
monitoring results of air quality and noise conducted at 1 air quality
monitoring station and 1 noise monitoring station described in the Monitoring
Proposal.
Table
2.1 Air
Quality Monitoring Equipment
Equipment |
Brand and
Model |
Portable direct reading dust meter |
Sibata Digital Dust Monitor (Model No.
LD-3 & LD-3B) |
High Volume Sampler |
Graseby Andersen Total Suspended
Particulate Mass Flow Controlled Sampling System (Model No. GMWS2310) |
Table 2.2 Locations
of Baseline Air Monitoring Stations
Monitoring Station |
Location |
Description |
AM7 |
West Kowloon No. 2 Sewage Pumping Station |
Rooftop of the premise |
Table 2.3 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and
Duration |
1-hour TSP |
3
times (at three consecutive Restricted Hours) per day while the highest dust impact was
expected, for 14 days |
24-hour TSP |
Daily,
for 14 days |
(a)
The HVS was installed in the vicinity of the air
sensitive receivers. The following
criteria were considered in the installation of the HVS.
(i)
A
horizontal platform with appropriate support to secure the sampler against
gusty wind to be provided.
(ii)
The
distance between the HVS and any obstacles, such as buildings, was at least twice
the height that the obstacle protrudes above the HVS.
(iii)
A
minimum of 2 meters separation from walls, parapets and penthouse for rooftop
sampler.
(iv)
A
minimum of 2 meters separation from any supporting structure, measured
horizontally is required;
(v)
No
furnace or incinerator flues nearby.
(vi)
Airflow
around the sampler to be unrestricted.
(vii)
Permission
to be obtained to set up the samplers and access to the monitoring stations.
(viii)
A
secured supply of electricity to be obtained to operate the samplers.
(ix)
The
sampler should be located more than 20 meters from any dripline.
(x)
Any
wire fence and gate, required to protect the sampler, should not obstruct the
monitoring process.
(xi)
Flow control accuracy was kept within ¡Ó2.5%
deviation over 24-hour sampling period.
(b)
Preparation of Filter Papers
(i)
Glass fibre filters, G810 were labelled and
sufficient filters that were clean and without pinholes were selected.
(ii)
All filters were equilibrated in the conditioning
environment for 24 Restricted Hours before weighing. The conditioning environment
temperature was around
(iii)
All filter papers were prepared and analysed by ALS
Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory and has
comprehensive quality assurance and quality control programmes.
(c)
Field Monitoring
(i)
The power supply was checked to ensure the HVS
works properly.
(ii)
The filter holder and the area surrounding the
filter were cleaned.
(iii)
The filter holder was removed by loosening the four
bolts and a new filter, with stamped number upward, on a supporting screen was
aligned carefully.
(iv)
The filter was properly aligned on the screen so
that the gasket formed an airtight seal on the outer edges of the filter.
(v)
The swing bolts were fastened to hold the filter
holder down to the frame. The
pressure applied was sufficient to avoid air leakage at the edges.
(vi)
Then the shelter lid was closed and was secured
with the aluminum strip.
(vii)
The HVS was warmed-up for about 5 minutes to
establish run-temperature conditions.
(viii)
A new flow rate record sheet was set into the flow
recorder.
(ix)
On site temperature and atmospheric pressure
readings were taken and the flow rate of the HVS was checked and adjusted at around
1.1 m3/min, and complied with the range specified in the updated
EM&A Manual (i.e. 0.6-1.7 m3/min).
(x)
The programmable digital timer was set for a
sampling period of 24 hrs, and the starting time, weather condition and the
filter number were recorded.
(xi)
The initial elapsed time was recorded.
(xii)
At the end of sampling, on site temperature and
atmospheric pressure readings were taken and the final flow rate of the HVS was
checked and recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully and folded
in half length so that only surfaces with collected particulate matter were in
contact.
(xv)
It was then placed in a clean plastic envelope and
sealed.
(xvi)
All monitoring information was recorded on a
standard data sheet.
(xvii)
Filters were then sent to ALS Technichem (HK) Pty
Ltd. for analysis.
(d)
Maintenance and Calibration
(i)
The HVS and its accessories were maintained in good
working condition, such as replacing motor brushes routinely and checking
electrical wiring to ensure a continuous power supply.
(ii)
HVSs were calibrated using TE
(iii)
Calibration certificate of the TE
(a)
Measuring Procedures
The measuring procedures of the 1-hour dust
meter were in accordance with the Manufacturer¡¦s Instruction Manual as follows:
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the ¡§TIME SETTING¡¨ switch to [BG]
(iv)
Push ¡§START/STOP¡¨ switch to perform background
measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert the
light scattering plate.
(vi)
Leave the equipment for 1 minute upon ¡§SPAN CHECK¡¨
is indicated in the display.
(vii)
Push ¡§START/STOP¡¨ switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE
position.
(ix)
Push the ¡§TIME SETTING¡¨ switch the time set in the
display to 3 Restricted Hours.
(x)
Lower down the air collection opening cover.
(xi)
Push ¡§START/STOP¡¨ switch to start measurement.
(b)
Maintenance and Calibration
(i)
The 1-hour TSP meter was calibrated at 1-year
intervals against a continuous particulate TEOM Monitor, Series 1400ab. Calibration certificates of the Laser
Dust Monitors are provided in Appendix A.
Table
2.4 Summary
of 1-hour TSP Baseline Monitoring Results
|
AM7 |
Average (£gg/m3) |
110 |
Range (£gg/m3) |
73 - 225 |
Table
2.5 Summary
of 24-hour TSP Baseline Monitoring Results
|
AM7 |
Average (£gg/m3) |
119 |
Range (£gg/m3) |
66 - 190 |
Table 2.6 Derivation
of Action and Limit Levels for Air Quality
Parameter |
Action Level |
Limit Level |
1-hour TSP Level in £gg/m3 |
For Baseline Level <384 £gg/m3, Action Level = (130% of baseline level + Limit level) ¡Ò 2 For Baseline Level > 384 £gg/m3, Action Level = Limit Level |
500 |
24-hour TSP
Level in £gg/m3 |
For Baseline Level <200 £gg/m3, Action Level = (130% of baseline level + Limit level) ¡Ò 2 For Baseline Level > 200 £gg/m3, Action Level = Limit Level
|
260 |
Table 2.7 Action
and Limit Levels for Air Quality
Parameter |
Monitoring Station |
Action Level (£gg/m3) |
Limit Level (£gg/m3) |
1-hour TSP
Level in £gg/m3 |
AM7 |
322 |
500 |
24-hour TSP Level in £gg/m3 |
AM7 |
207 |
260 |
Table 3.1 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated Sound Level
Meter |
B&K (Model No.
2238, 2250L and 2270) |
Acoustic Calibrator |
B&K (Model No.
4231) |
Table 3.2 Locations
of Baseline Noise Monitoring Station
Monitoring Station |
Location |
Description |
NM6 |
Customs¡¦ Marine
Base |
1m from the exterior of the roof façade of Block H of Government
Dockyard |
Table 3.3 Noise
Monitoring Parameters, Frequency and Duration
Time Period |
Duration, min |
Parameters |
Daytime: 0700-1900
hrs on normal weekdays |
30 (Leq(30-min)) |
Leq, L90
& L10 |
Evening: 1900-2300
hrs on normal weekdays |
15 (3 consecutive Leq(5-min)) |
|
General
Holidays and Sundays: 0700-2300
hrs |
||
Night-time: 2300-0700
hrs of next day on all days |
(a)
Façade measurements (i.e. 1m from the exterior of
the building façade) were made at all monitoring locations.
(b)
The battery condition was checked to ensure the
correct functioning of the meter.
(c)
Parameters such as frequency weighting, the time
weighting and the measurement time were set as follows:
(i)
frequency weighting: A
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes) during
non-restricted Restricted Hours i.e. 07:00 ¡V 1900 on normal weekdays; Leq(5-minutes) x3
during restricted Restricted Hours i.e. 19:00
¡V 23:00 and 23:00 ¡V 07:00 of normal weekdays, whole day of Sundays and Public
Holidays
(d)
Prior to and after each noise measurement, the
meter was calibrated using the acoustic calibrator for 94dB(A) at 1000 Hz. If the difference in the calibration
level before and after measurement was more than 1 dB(A), the measurement would
be considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
(e)
During the monitoring period, the Leq, L10
and L90 were recorded.
In addition, site conditions and noise sources were recorded on a
standard record sheet.
(f)
Noise measurement was paused during periods of high
intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations
were recorded when intrusive noise was unavoidable.
(g)
Noise monitoring was cancelled in the presence of
fog, rain, wind with a steady speed exceeding
(a)
The microphone head of the sound level meter was
cleaned with soft cloth at regular intervals.
(b)
The meter and calibrator were sent to the supplier
or HOKLAS laboratory to check and calibrate at yearly intervals.
(c)
Calibration certificates of the sound level meters
and acoustic calibrators are provided in Appendix
A.
Table 3.4 Summary
of Baseline Noise Monitoring Results
Time period |
30-min Mean
of Noise Levels for time period (1) / 5-min Mean of Noise Levels for time period (2, (3) & (4), dB(A) |
Range, dB(A) |
||
Leq |
L10 |
L90 |
Leq |
|
(1) 0700-1900
hrs on normal weekdays |
76.5 |
77.5 |
75.0 |
70.8 ¡V 78.9 |
(2) 1900-2300
hrs on normal weekdays |
60.4 |
62.1 |
58.3 |
58.4 ¡V 63.8 |
(3) 0700-2300 hrs on General Holidays and Sundays |
61.5 |
64.1 |
58.7 |
58.6 ¡V 64.4 |
(4) 2300-0700
hrs of next day on
all days |
59.6 |
60.5 |
58.2 |
58.0 ¡V 61.0 |
Table 3.7 Criteria for
Action and Limit Levels for Construction Noise
Time
Period |
Action
Level |
Limit
Levels |
0700-1900 hrs of normal weekdays |
When one documented complaint is received |
75 dB(A)* |
Table 3.8 Action and
Limit Levels for Construction Noise of the Project
Time
Period |
Monitoring
Station |
Action
Level |
Limit
Levels |
0700-1900 hrs on normal weekdays |
NM6 |
When one documented complaint is received |
75 dB(A) |
1900-2300 hrs on normal weekdays, 0700-2300 hrs on
General Holidays and Sundays |
NM6 |
When one documented complaint is received |
70 dB(A) |
2300-0700 hrs of
next day on all days |
NM6 |
When one documented complaint is received |
55 dB(A) |