TABLE OF CONTENTS

 

1       introduction

2       Air quality monitoring

2.1     Monitoring Requirements

2.2     Monitoring Equipment

2.3     Monitoring Locations

2.4     Monitoring Parameters, Frequency and Duration

2.5     Monitoring Methodology

2.6     Results and Observations

2.7     Action and Limit Levels

3       Noise MONITORING

3.1     Monitoring Requirements

3.2     Monitoring Equipment

3.3     Monitoring Locations

3.4     Monitoring Parameters, Frequency and Duration

3.5     Monitoring Methodology

3.6     Results and Observations

3.7     Action and Limit Levels

4       Conclusion

 

 

List of Tables

Table 2.1         Air Quality Monitoring Equipment

Table 2.2         Locations of Baseline Air Monitoring Stations

Table 2.3         Air Quality Monitoring Parameters, Frequency and Duration

Table 2.4         Summary of 1-hour TSP Baseline Monitoring Results

Table 2.5         Summary of 24-hour TSP Baseline Monitoring Results

Table 2.6         Derivation of Action and Limit Levels for Air Quality

Table 2.7         Action and Limit Levels for Air Quality

Table 3.1         Noise Monitoring Equipment

Table 3.2         Locations of Baseline Noise Monitoring Station

Table 3.3         Noise Monitoring Parameters, Frequency and Duration

Table 3.4         Summary of Baseline Noise Monitoring Results

Table 3.7         Criteria for Action and Limit Levels for Construction Noise

Table 3.8         Action and Limit Levels for Construction Noise of the Project

 

 

Figures

 

Figure 1.1      Site Layout Plan

Figure 2.1      Locations of Air Quality Monitoring Stations During Baseline Monitoring

Figure 3.1      Location of Noise Monitoring Stations During Baseline Monitoring

 

 

List of Appendix

 

Appendix A    Calibration Certificates of Monitoring Equipments

Appendix B    Baseline Air Quality Monitoring Results

Appendix C    Baseline Noise Monitoring Results

 

 

EXECUTIVE SUMMARY

The proposed construction of interconnection tunnel and diaphragm wall for main pumping station at Stonecutters Island Sewage Treatment Works (SCISTW) (the Project) is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is governed by an Environmental Permit (EP-322/2008/B). The Project comprises the construction of Interconnection Tunnel between the Inlet Chamber of the Main Pumping Station and the existing Riser Shaft and diaphragm wall for the Main Pumping Station

In accordance with the Environmental Monitoring and Audit Manual (EM&A Manual) of the Project, baseline monitoring of air quality and noise is required prior to commencement of construction of the Project. As accesses to some of the proposed monitoring stations as stipulated in the EM&A manual have been rejected by other parties or found to be not available or not suitable, a Monitoring Proposal, presenting the alternative monitoring stations, requirements and methodologies for the monitoring, was submitted.

This report documents the baseline monitoring of air quality at 1 monitoring station and noise monitoring at 1 monitoring station as described in the Monitoring Proposal. For monitoring station at Block A of Government Dockyard mentioned in the Monitoring Proposal, as monitoring station will be established by the Contract DE/2009/02 (Provision of Covers and Deodourisation Facilities to the Existing Sedimentation Tanks at SCISTW), so baseline monitoring details at this station are not mentioned in this report.

The baseline monitoring of both air quality and noise was carried out between 23 November 2009 and 6 December 2009. Air quality was recorded in terms of 1-hour Total Suspended Particulates (TSP) and 24-hour TSP. The weather during the monitoring period was mainly sunny. For baseline noise levels, Leq­(30-minute) were recorded for non-restricted Restricted Hours (07:00 ¡V 19:00 on normal weekdays) and L­eq(5-minute) were recorded for restricted Restricted Hours (19:00 ¡V 23:00 and 23:00 ¡V 07:00 of next day on normal weekdays, whole day on General Holidays and Sundays).

The averaged 1-hour TSP levels and 24-hour TSP levels at AM7 are summarized as follows:

Air quality monitoring location

AM7

Averaged 1-hr TSP (£gg/m3)

110

Averaged 24-hr TSP (£gg/m3)

119

The averaged baseline noise levels are summarized in the following table:

Noise monitoring location

NM6

Averaged baseline noise level during daytime on normal weekdays

(Leq(30 min), dB(A))

76.5

Averaged baseline noise level during evening on normal weekdays

(Leq(5 min), dB(A))

60.4

Averaged baseline noise level during daytime and evening on  General Holidays and Sundays

(Leq(5 min), dB(A))

61.5

Averaged baseline noise level during night-time on all days

(Leq(5 min), dB(A))

59.6


 

1             introduction

1.1.      Background

 

1.1.1.     China State - Shanghai Tunnel Joint Venture was awarded the Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A ¡V Construction of Interconnection Tunnel and Diaphragm Wall for Main Pumping Station at Stonecutters Island Sewage Treatment Works (SCISTW) (the Project) from Drainage Services Department (DSD) of the Government of the Hong Kong Special Administrative Region. The Project comprises the construction of Interconnection Tunnel between the Inlet Chamber of the Main Pumping Station and the existing Riser Shaft and diaphragm wall for the Main Pumping Station. The site layout plan and the Works site boundary are shown in Figure 1.1.

 

1.1.2.     The Project is a designated project and is governed by an Environmental Permit (EP-322/2008/B).

 

1.1.3.     The scope of the Project comprises mainly:

 

n    

l   Construction of Interconnection Tunnel with concrete lining between the Inlet Chamber of the Main Pumping Station and the existing Riser Shaft;

l   Construction of diaphragm wall, base slab and pile cap for the Main Pumping Station and its Inlet Chamber;

l   Excavation within the diaphragm walls for the Main Pumping Station and its  Inlet Chamber to founding levels;

l   Piling works for the Main Pumping Stations;

l   Utilities upgrading and diversion works;

l   Temporary launching shaft to be handed over to MPS Contractor;

l   Carrying out ground monitoring and instrumentation works;

l   Carrying out pumping test;

l   Miscellaneous building, civil and electrical and mechanical works; and

l   Landscape works.

 

1.1.4.     In accordance with the EM&A Manual of the Project, environmental baseline conditions were established by the ET prior to the commencement of construction of the Project.

 

1.1.5.     As accesses to some of the proposed monitoring stations as stipulated in the EM&A manual have been rejected by other parties or found to be not available or not suitable, a Monitoring Proposal, presenting the alternative monitoring stations, requirements and methodologies for the monitoring, was submitted.

 

1.1.6.     Baseline monitoring was undertaken and baseline monitoring report was prepared prior to commencement of construction of the Project.

 

1.2.      Purpose of the Baseline Monitoring Report

 

1.2.1.     The purpose of this report is to review the baseline conditions of the Project site and to establish baseline levels for air and noise in accordance with the EM&A Manual and Monitoring Proposal. These levels would be used as the basis for assessing environmental impact and compliance during construction of the Project.

 

1.2.2.     This baseline monitoring report presents the baseline monitoring requirements, methodologies and monitoring results of air quality and noise conducted at 1 air quality monitoring station and 1 noise monitoring station described in the Monitoring Proposal.

 

 

 

 

 

 

 

2             Air quality monitoring

 

2.1          Monitoring Requirements

2.1.1       In accordance with the EM&A Manual and the Monitoring Proposal, baseline 1-hour and 24-hour TSP levels at 2 air quality monitoring stations should be established by conducting baseline 1-hour and 24-hour TSP monitoring for at least 14 days.

2.2          Monitoring Equipment

2.2.1       24-hour TSP air quality monitoring was performed using High Volume Sampler (HVS) located at designated monitoring station. The HVS meets all the requirements of the EM&A Manual.  Portable direct reading dust meter was used to carry out the 1-hour TSP monitoring at designated monitoring station.  Brand and model of the equipment is given in Table 2.1.

  Table 2.1          Air Quality Monitoring Equipment

Equipment

Brand and Model

Portable direct reading dust meter

Sibata Digital Dust Monitor (Model No. LD-3 & LD-3B)

 

 

High Volume Sampler

Graseby Andersen Total Suspended Particulate Mass Flow Controlled Sampling System (Model No. GMWS2310)

 

2.3          Monitoring Locations

2.3.1       Monitoring location at Block A of Government Dockyard stated in the Monitoring Proposal, which monitoring station had been set up at the proposed location by the other contract (HATS Stage 2A ¡V Provision of Advanced Disinfection Facilities (ADF) at SCISTW) in the Year 2008, will be established by the Contract DE/2009/02 (Provision of Covers and Deodourisation Facilities to the Existing Sedimentation Tanks at SCISTW). Therefore, no baseline monitoring details at this station are mentioned in this report.

2.3.2       Monitoring location AM7 was set up at the proposed location in accordance with the Monitoring Proposal and as agreed by the ER and the IEC. Figure 2.1 shows the location of monitoring station. Table 2.2 describes the details of the monitoring stations.

  Table 2.2          Locations of Baseline Air Monitoring Stations

Monitoring Station

Location

Description

AM7

West Kowloon No. 2

Sewage Pumping Station

Rooftop of the premise

 

 


 

2.4          Monitoring Parameters, Frequency and Duration

2.4.1       Table 2.3 summarizes the monitoring parameters, frequency and duration of baseline TSP monitoring.

  Table 2.3          Air Quality Monitoring Parameters, Frequency and Duration

Parameter

Frequency and Duration

1-hour TSP

3 times (at three consecutive Restricted Hours) per day while the highest dust impact was expected, for 14 days

24-hour TSP

Daily, for 14 days

 

2.5          Monitoring Methodology

2.5.1       24-Hr TSP Monitoring

(a)           The HVS was installed in the vicinity of the air sensitive receivers.  The following criteria were considered in the installation of the HVS.

 

(i)             A horizontal platform with appropriate support to secure the sampler against gusty wind to be provided.

(ii)            The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.

(iii)           A minimum of 2 meters separation from walls, parapets and penthouse for rooftop sampler.

(iv)          A minimum of 2 meters separation from any supporting structure, measured horizontally is required;

(v)           No furnace or incinerator flues nearby.

(vi)          Airflow around the sampler to be unrestricted.

(vii)         Permission to be obtained to set up the samplers and access to the monitoring stations.

(viii)        A secured supply of electricity to be obtained to operate the samplers.

(ix)          The sampler should be located more than 20 meters from any dripline.

(x)           Any wire fence and gate, required to protect the sampler, should not obstruct the monitoring process.

(xi)          Flow control accuracy was kept within ¡Ó2.5% deviation over 24-hour sampling period.

 

(b)           Preparation of Filter Papers

 

(i)             Glass fibre filters, G810 were labelled and sufficient filters that were clean and without pinholes were selected.

(ii)            All filters were equilibrated in the conditioning environment for 24 Restricted Hours before weighing. The conditioning environment temperature was around 25 ¢XC and not variable by more than ¡Ó3 ¢XC; the relative humidity (RH) was < 50% and not variable by more than ¡Ó5%. A convenient working RH was 40%.

(iii)           All filter papers were prepared and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory and has comprehensive quality assurance and quality control programmes.

 

(c)           Field Monitoring

 

(i)             The power supply was checked to ensure the HVS works properly.

(ii)            The filter holder and the area surrounding the filter were cleaned.

(iii)           The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.

(iv)          The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.

(v)           The swing bolts were fastened to hold the filter holder down to the frame.  The pressure applied was sufficient to avoid air leakage at the edges.

(vi)          Then the shelter lid was closed and was secured with the aluminum strip.

(vii)         The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.

(viii)        A new flow rate record sheet was set into the flow recorder.

(ix)          On site temperature and atmospheric pressure readings were taken and the flow rate of the HVS was checked and adjusted at around 1.1 m3/min, and complied with the range specified in the updated EM&A Manual (i.e. 0.6-1.7 m3/min).

(x)           The programmable digital timer was set for a sampling period of 24 hrs, and the starting time, weather condition and the filter number were recorded.

(xi)          The initial elapsed time was recorded.

(xii)         At the end of sampling, on site temperature and atmospheric pressure readings were taken and the final flow rate of the HVS was checked and recorded.

(xiii)        The final elapsed time was recorded.

(xiv)        The sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.

(xv)         It was then placed in a clean plastic envelope and sealed.

(xvi)        All monitoring information was recorded on a standard data sheet.

(xvii)       Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.

 

(d)           Maintenance and Calibration

 

(i)             The HVS and its accessories were maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.

(ii)            HVSs were calibrated using TE-5025A Calibration Kit prior to the commencement of baseline monitoring.

(iii)           Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in Appendix A.

 

 

2.5.2       1-hour TSP Monitoring

(a)           Measuring Procedures

 

The measuring procedures of the 1-hour dust meter were in accordance with the Manufacturer¡¦s Instruction Manual as follows:

(i)             Turn the power on.

(ii)            Close the air collecting opening cover.

(iii)           Push the ¡§TIME SETTING¡¨ switch to [BG]

(iv)          Push ¡§START/STOP¡¨ switch to perform background measurement for 6 seconds.

(v)           Turn the knob at SENSI ADJ position to insert the light scattering plate.

(vi)          Leave the equipment for 1 minute upon ¡§SPAN CHECK¡¨ is indicated in the display.

(vii)         Push ¡§START/STOP¡¨ switch to perform automatic sensitivity adjustment. This measurement takes 1 minute.

(viii)        Pull out the knob and return it to MEASURE position.

(ix)          Push the ¡§TIME SETTING¡¨ switch the time set in the display to 3 Restricted Hours.

(x)           Lower down the air collection opening cover.

(xi)          Push ¡§START/STOP¡¨ switch to start measurement.

 

(b)           Maintenance and Calibration

 

(i)             The 1-hour TSP meter was calibrated at 1-year intervals against a continuous particulate TEOM Monitor, Series 1400ab.  Calibration certificates of the Laser Dust Monitors are provided in Appendix A.

 

2.6          Results and Observations

2.6.1       The baseline monitoring at the Monitoring Station AM7 was carried out between 23 November 2009 and 6 December 2009, during which, the weather was mostly sunny. Although construction works from other contract, about 280m away from the Monitoring Station AM7, were being carried out during some days in the monitoring period (from 1 Dec 2009 to 5 Dec 2009), the construction works was considered not contributing to major dust emissions as the construction works during the abovementioned 5 days included only diaphragm wall construction by hydromill method and removal of excavated materials including marine deposit generated from the diaphragm wall construction.

2.6.2       Baseline 1-hour TSP and 24-hour TSP monitoring for the Monitoring Station AM7 was carried out from 23 November 2009 to 6 December 2009 for consecutively 14 days.

2.6.3       The baseline monitoring results for 1-hour TSP and 24-hour TSP are summarized in Table 2.4 and 2.5 respectively. Detailed air quality monitoring results for Monitoring Station AM7 are presented in Appendix B.

  Table 2.4          Summary of 1-hour TSP Baseline Monitoring Results

 

AM7

Average (£gg/m3)

110

Range (£gg/m3)

73 - 225

  Table 2.5          Summary of 24-hour TSP Baseline Monitoring Results

 

AM7

Average (£gg/m3)

119

Range (£gg/m3)

66 - 190

 

2.7          Action and Limit Levels

2.7.1       The air quality monitoring results, in terms of 1-hour TSP and 24-hour TSP were below the Limit Level set out in the Air Quality Objective (AQO) at both monitoring locations.

2.7.2       The Action and Limit Levels for air quality impact monitoring were based on the criteria adopted from the EM&A Manual as presented in Table 2.6.

 


 

Table 2.6                        Derivation of Action and Limit Levels for Air Quality

Parameter

Action Level

Limit Level

1-hour TSP  Level in £gg/m3

 

 

 

 

For Baseline Level <384 £gg/m3,

Action Level = (130% of baseline level + Limit level) ¡Ò 2

For Baseline Level > 384 £gg/m3,

Action Level =  Limit Level

500

24-hour TSP Level in £gg/m3

 

 

 

For Baseline Level <200 £gg/m3,

Action Level = (130% of baseline level + Limit level) ¡Ò 2

For Baseline Level > 200 £gg/m3,

Action Level =  Limit Level

260

 

2.7.3       Table 2.7 shows the derived Action and Limit Levels for air quality impact monitoring for the Project.

  Table 2.7          Action and Limit Levels for Air Quality

Parameter

Monitoring Station

Action Level (£gg/m3)

Limit Level (£gg/m3)

1-hour TSP  Level in £gg/m3

AM7

322

500

24-hour TSP Level in £gg/m3

AM7

207

260

 


3             Noise MONITORING

3.1          Monitoring Requirements

3.1.1      In accordance with the EM&A Manual and the Monitoring Proposal, baseline noise levels at 1 monitoring station should be established by conducting daily noise monitoring for 2 weeks.

3.2          Monitoring Equipment

3.2.1       Noise monitoring was performed using sound level meter at each designated monitoring station.  The sound level meters deployed comply with the International Electrotechnical Commission Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level.  Brand and model of the equipment is given in Table 3.1.

  Table 3.1          Noise Monitoring Equipment

Equipment

Brand and Model

Integrated Sound Level Meter

B&K (Model No. 2238, 2250L and 2270)

Acoustic Calibrator

B&K (Model No. 4231)

 

 

 

3.3          Monitoring Locations

3.3.1       Monitoring station NM6 was set up at the proposed locations in accordance with the Monitoring Proposal.  Figure 3.1 shows the location of the monitoring station. Table 3.2 describes the details of the monitoring station.

  Table 3.2          Locations of Baseline Noise Monitoring Station

Monitoring Station

Location

Description

NM6

Customs¡¦ Marine Base

1m from the exterior of the roof façade of Block H of Government Dockyard

 

3.4          Monitoring Parameters, Frequency and Duration

3.4.1       Table 3.3 summarizes the monitoring parameters, frequency and duration of baseline noise monitoring.

  Table 3.3          Noise Monitoring Parameters, Frequency and Duration

Time Period

Duration, min

Parameters

Daytime:

0700-1900 hrs on normal weekdays

30 (Leq(30-min))

Leq, L90 & L10

Evening:

1900-2300 hrs on normal weekdays

15 (3 consecutive Leq(5-min))

General Holidays and Sundays:

0700-2300 hrs

Night-time:

2300-0700 hrs of next day on all days

 

3.5          Monitoring Methodology

3.5.1       Monitoring Procedure

(a)           Façade measurements (i.e. 1m from the exterior of the building façade) were made at all monitoring locations.

(b)           The battery condition was checked to ensure the correct functioning of the meter.

(c)           Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

(i)             frequency weighting: A

(ii)            time weighting: Fast

(iii)           time measurement: Leq(30-minutes) during non-restricted Restricted Hours i.e. 07:00 ¡V 1900 on normal weekdays; Leq(5-minutes) x3 during restricted Restricted Hours i.e. 19:00 ¡V 23:00 and 23:00 ¡V 07:00 of normal weekdays, whole day of Sundays and Public Holidays

(d)           Prior to and after each noise measurement, the meter was calibrated using the acoustic calibrator for 94dB(A) at 1000 Hz.  If the difference in the calibration level before and after measurement was more than 1 dB(A), the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

(e)           During the monitoring period, the Leq, L10 and L90 were recorded.  In addition, site conditions and noise sources were recorded on a standard record sheet.

(f)            Noise measurement was paused during periods of high intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations were recorded when intrusive noise was unavoidable.

(g)           Noise monitoring was cancelled in the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind with gusts exceeding 10m/s.

 

3.5.2       Maintenance and Calibration

(a)           The microphone head of the sound level meter was cleaned with soft cloth at regular intervals.

(b)           The meter and calibrator were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.

(c)           Calibration certificates of the sound level meters and acoustic calibrators are provided in Appendix A.

3.6          Results and Observations

3.6.1       There was no other major activity influencing the measured noise level during the baseline noise monitoring period. The dominant noise sources were from community noises and nearby cargos.

3.6.2       Baseline noise monitoring was conducted for consecutively 2 weeks, from 23 November 2009 to 6 December 2009.

3.6.3       The baseline noise monitoring results are summarized in Tables 3.4 to 3.6. Detailed noise monitoring results are presented in Appendix C.

 

            Table 3.4          Summary of Baseline Noise Monitoring Results

Time period

30-min Mean of Noise Levels for time period (1) /

5-min Mean of Noise Levels for time period

(2, (3) & (4),

dB(A)

Range, dB(A)

Leq

L10

L90

Leq

(1) 0700-1900 hrs on normal weekdays

76.5

77.5

75.0

70.8 ¡V 78.9

(2) 1900-2300 hrs on normal weekdays

60.4

62.1

58.3

58.4 ¡V 63.8

(3) 0700-2300 hrs on  General Holidays and Sundays

61.5

64.1

58.7

58.6 ¡V 64.4

(4) 2300-0700 hrs of    next day on all days

59.6

60.5

58.2

      58.0 ¡V 61.0

    

 

3.6.4       Although no construction work was carried out in the vicinity during the course of measurement, the averaged baseline daytime noise levels recorded at the monitoring location exceeded the Limit Level of 75dB(A).

3.6.5       The averaged baseline night-time noise monitoring results exceeded the criteria of 55dB(A) at the monitoring location.

 

3.7          Action and Limit Levels

3.7.1       The Action and Limit Levels of noise monitoring have been set in accordance with the derivation criteria specified in the EM&A Manual as shown in Table 3.7 below.

Table 3.7          Criteria for Action and Limit Levels for Construction Noise

Time Period

Action Level

Limit Levels

0700-1900 hrs of

normal weekdays

When one documented complaint is received

75 dB(A)*

 

Notes: If works are to be carried out during restricted Restricted Hours, the conditions stipulated in the Construction Noise Permit (CNP) issued by the Noise Control Authority have to be followed.

* 70 dB(A) and 65 dB(A) for schools during normal teaching periods and school examination periods, respectively.

 

3.7.2       The Project area is within non-designated area under the Noise Control Ordinance (NCO) while Area Sensitivity Ratings of the noise sensitive receivers (NSRs) of the Projects are considered as ¡§C¡¨ as they are directly affected industrial areas.  With considering the monitoring location NM6 is not a NSR and it serves as the only accessible alternative monitoring location for the planned monitoring location at Planned FSD Diving Rescue and Diving Training Centre (named as M11 in the EM&A Manual), the Limit Level as stipulated in the EM&A Manual is adopted. The Action and Limit Levels for impact noise monitoring are derived and presented in Table 3.8 below.

 

Table 3.8          Action and Limit Levels for Construction Noise of the Project

Time Period

Monitoring Station

Action Level

Limit Levels

0700-1900 hrs on

normal weekdays

NM6

When one documented complaint is received

75 dB(A)

1900-2300 hrs on normal weekdays, 0700-2300 hrs on General Holidays and Sundays

NM6

When one documented complaint is received

70 dB(A)

2300-0700 hrs of next day on all days

NM6

When one documented complaint is received

55 dB(A)

 


4             Conclusion

4.1.1       Baseline air quality monitoring was carried out from 23 November 2009 to 6 December 2009 at 1 monitoring station AM7. Action Level for air quality at monitoring station AM7 was derived from the baseline monitoring results recorded.  For monitoring station at Block A of Government Dockyard mentioned in the Monitoring Proposal, as monitoring station will be established by the Contract DE/2009/02 (Provision of Covers and Deodourisation Facilities to the Existing Sedimentation Tanks at SCISTW), so no baseline monitoring details at this station are mentioned in this report.

4.1.2       Baseline noise monitoring was carried out from 23 November 2009 to 6 December 2009 at 1 monitoring station NM6. The Action Level of construction noise is based on documented complaints received, while the Limit Level is the level at a specific limit according to EIAO-TM in daytime and NCO during restricted Restricted Hours.

4.1.3       The averaged baseline daytime noise levels recorded at Customs¡¦ Marine Base (NM6) exceeded the Limit Level of 75dB(A).

4.1.4       The averaged baseline night-time noise monitoring results exceeded the criteria of 55dB(A) at monitoring location.