Contract No.DC/2009/23
Harbour Area Treatment Scheme Stage 2A - Upgrading of Preliminary Treatment Works at North Point, Wan Chai East and Central
Scope of Works
The works include the construction of fine screen and grit trap buildings, deodorization rooms, administration building and modification of existing inlet pumping stations at the preliminary treatment works at North Point, Wan Chai East and Central
Contract Particulars
Contract Commencement : 06/01/2011
Completion Date : 30/06/2016
Contract Sum : $797.8 million
Government Department : Drainage Services Department
Consultant :Ove Arup & Partners Hong Kong Ltd.
Contractor : Leader - JEC Joint Venture