• Decoration IconDrainage Hotline 2300 1110
  • Code on Access to information Icon
  • FAQ Icon
  • Useful Links Icon
  • DSD Facebook
  • DSD Instagram
  • DSD Youtube
Decoration IconDrainage Hotline 2300 1110

Drainage Services Department

PWP No. 4434DS

Village Sewerage in Fanling Wai, So Kwun Po and Leng Pei Tsuen, Fanling

Project Scope

The scope of the project comprises the construction of about 6 kilometres of sewers in three unsewered areas in Fanling, namely Fanling Wai, So Kwun Po and Leng Pei Tsuen, Fanling

Major Improvements and Benefits

To improve environmental hygiene and further reduce the amount of pollutants being discharged into the nearby River Indus and Deep Bay.

Consultants

Atkins China Limited

Contractor

Welcome Construction Company Limited

Contract No.
DC/2020/01
Project Commencement Date
13 January 2021
Project Completion Date
Mid 2025
Project estimate

About $180 million

Controlling Division
Harbour Area Treatment Scheme Division
Type
Sewerage and sewage treatment
District
North
Status
On-going
Other Information
Back to Top