PWP No. 4419DS
Construction and rehabilitation of sewage rising mains in Tai Po Kau
Rehabilitation of 1 section of existing sewage rising main and construction of a new sewage rising main with a total length of about 0.8 km alongside the existing one
The construction and rehabilitation works will adequately improve the reliability of the concerned parts of the sewerage network
Meinhardt Infrastructure and Environment Limited
Hing & Cheong Company Limited
DC/2021/03
30 September 2021
30 September 2023
About $107.6 million
Consultants Management Division
Sewerage and sewage treatment
Tai Po
Completed