PWP No. 4378DS

North District Sewerage, Stage 2 Part 2A - Pak Hok Lam Trunk Sewer and Sha Tau Kok Village Sewerage

Project Scope
The scope of the project comprises the construction of about 2 km of trunk sewers along Sha Tau Kok Road; about 7.5 km of sewers for the nine unsewered areas; and one sewage pumping station at Wu Shek Kok with associated twin rising mains.
Major Improvements and Benefits
To improve the water quality of Deep Bay and the sanitary condition in 9 unsewered areas.
Consultants
Black & Veatch Hong Kong Limited
Contractor
DC/2012/09 – Kum Shing (K.F.) Construction Co. Ltd.
Contract No.
DC/2012/09
Project Commencement Date
28 June 2012
Project Completion Date
19 January 2017
Project estimate
Approx. $272M
Controlling Division
Consultants Management Division
Type
Sewerage and sewage treatment
District
North
Status
Completed