PWP No. 4180CD
Rehabilitation of underground stormwater drains stage 1
Project Scope
The scope of the project comprises condition survey of about 35 kilometres (km) of underground stormwater drains and associated manholes distributed throughout the territory; rehabilitation of about 11 km of underground stormwater drains distributed throughout the territory; and ancillary works.
Major Improvements and Benefits
To improve the reliability of the concerned drainage system
Consultants
Binnies Hong Kong Limited
Contractor
Kwan On Construction Company Limited
Contract No.
DC/2018/10
Project Commencement Date
14 January 2019
Project Completion Date
31 December 2022
Project estimate
About $122.8 million
Controlling Division
Planning and Rehabilitation Division
Type
Flood Prevention
District
Central & Western; Eastern; Southern; Wan Chai; Islands; Kwun Tong; Kowloon City; Sham Shui Po; Wong Tai Sin; Yau Tsim Mong; Kwai Tsing; North; Sai Kung; Sha Tin; Tai Po; Tsuen Wan; Tuen Mun; Yuen Long
Status
Completed
Other Information