PWP No. 4175CD
Drainage Improvement Works in Tsim Sha Tsui
Project Scope
Construction of an underground stormwater pumping station and associated pipeworks at the vicinity of Chatham Road South
Major Improvements and Benefits
To improve the conveyance capacity of the drainage network and relieve the flood risk in Chatham Road South and adjacent areas in Tsim Sha Tsui
Consultants
Meinhardt Infrastructure and Environment Limited
Contractor
CW-KL JV (Chun Wo Construction and Engineering Company Limited – Kwan Lee Holding Limited Joint Venture)
Contract No.
DC/2022/01
Project Commencement Date
19 August 2022
Project Completion Date
Mid 2027
Project estimate
About $952.6 million
Controlling Division
Harbour Area Treatment Scheme Division
Type
Flood Prevention
District
Yau Tsim Mong
Status
On-going
Other Information